How would you bid a passenger train clean? They also have a cafe that seats 50. What productivity rate can you use?


Answer

You would probably be looking at a cleaning production rate of 700 sq. ft. per hour (plus or minus 20%) depending upon passenger occupancy and use. You would then add a day porter if it must be kept clean while occupied.